ПЛАНИРАНО ПРЕКЪСВАНЕ НА ПРЕНОСЕН ГАЗОПРОВОД Dn500, УЧАСТЪК ЛОЗАРЕВО - БУРГАС
Актуализация: промяна на началната и крайната дата на ремонтините дейности
Начало: 22.04.2025, 12:00 EET
Край: 25.04.2025, 12:00 EET
Поради планирани ремонтни работи по преносен газопровод Dn500, участък Лозарево - Бургас, в периода 22.04.2025 (12:00 EET) – 25.04.2025 (12:00 ЕЕТ) ще бъде преустановено подаването на природен газ (разполагаем капацитет равен на нула) в изходни точки:
0 kWh/d - GRS Burgas C059P01 exit, 58ZC059P01BURG-Z
0 kWh/d - GRS Burgas C059P02 exit, 58ZC059P02BURG-S
0 kWh/d - GRS Burgas C059P03 exit, 58ZC059P03BURG-L
0 kWh/d - GRS Burgas C059P04 exit, 58ZC059P04BURG-E
0 kWh/d - AGRS Debelt C060P01 exit, 58ZC060P01DEBL-9
0 kWh/d - AGRS Debelt C060P02 exit, 58ZC060P02DEBL-2
0 kWh/d - AGRS Kameno C061P01 exit, 58ZC061P01KAMN-1
0 kWh/d - AGRS Kameno C061P02 exit, 58ZC061P02KAMN-V
0 kWh/d - AGRS Kameno C061P03 exit, 58ZC061P03KAMN-O
0 kWh/d - GMS Debelt Emi C062P01 exit, 58ZC062P01EMI--I
ПОВЕЧЕ ИНФОРМАЦИЯ ЗА СЪБИТИЕТО Е ПУБЛИКУВАНА НА BGH IIP *
*Съгласно Член 4(1) и Член 4а на REMIT II (Регламент (ЕС) 2024/1106 за изменение на регламенти (ЕС) №1227/2011 и (ЕС) 2019/942), участниците на пазара разкриват вътрешна информация чрез платформи за вътрешна информация, оторизирани от ACER.
Информация за планираните ремонтни дейности по газопреносната система на "Булгартрансгаз" ЕАД
PLANNED INTERRUPTION AT TRANSMISSION GAS PIPELINE DN500, PIPELINE SECTION LOZAREVO - BURGAS
Update: changed start date and end date of the maintenance works
Event start: 22.04.2025, 12:00 EET
Event end: 25.04.2025, 12:00 EET
Due to planned repair works at transmission gas pipeline Dn500, pipeline section Lozarevo - Burgas, the natural gas supply will be stopped (available capacity equal to zero) within the period 22.04.2025 (12:00 EET) – 25.04.2025 (12:00 ЕЕТ) at the exit points:
0 kWh/d - GRS Burgas C059P01 exit, 58ZC059P01BURG-Z
0 kWh/d - GRS Burgas C059P02 exit, 58ZC059P02BURG-S
0 kWh/d - GRS Burgas C059P03 exit, 58ZC059P03BURG-L
0 kWh/d - GRS Burgas C059P04 exit, 58ZC059P04BURG-E
0 kWh/d - AGRS Debelt C060P01 exit, 58ZC060P01DEBL-9
0 kWh/d - AGRS Debelt C060P02 exit, 58ZC060P02DEBL-2
0 kWh/d - AGRS Kameno C061P01 exit, 58ZC061P01KAMN-1
0 kWh/d - AGRS Kameno C061P02 exit, 58ZC061P02KAMN-V
0 kWh/d - AGRS Kameno C061P03 exit, 58ZC061P03KAMN-O
0 kWh/d - GMS Debelt Emi C062P01 exit, 58ZC062P01EMI--I
MORE DETAILS ABOUT THE EVENT ARE PUBLISHED ON BGH IIP *
*According to Article 4(1) and Article 4a of REMIT II (Regulation (EU) 2024/1106 amending regulations (EU) № 1227/2011 and (EU) 2019/942), market participants shall disclose the inside information through inside information platforms authorized by ACER.
Information on scheduled maintenance activities along Bulgartransgaz's transmission system