PROJECT OF COMMON INTEREST 6.8.2

REHABILITATION, MODERNIZATION AND EXPANSION OF THE EXISTING GAS TRANSMISSION SYSTEM

 (PCI 6.8.2)

PCI 6.8.2 represents a complex, multicomponent, staged project for modernization, rehabilitation and expansion of the existing gas transmission infrastructure on the territory of Bulgaria, owned and operated by the combined gas operator Bulgartransgaz EAD.

The project has been implemented in 3 time phases and includes the following activities:

Modernization and rehabilitation of compressor stations;

  • Modernization and rehabilitation of compressor stations;
  • Repair and replacement of gas pipeline sections following inspections;
  • Expansion and modernization of the existing gas transmission network;
  • Inspections to determine and characterize the gas pipelines' condition;
  • Implementation of systems for optimization of the management process of the network technical condition.

 

 Current PCI 6.8.2 implementation status (PHASE 2):

CONSTRUCTION ACTIVITIES

  • On 30.11.2021, the second stage of modernisation of three compressor stations came to an end.

CS Petrich - commissioned in February 2021

CS Ihtiman - commissioned in November 2021

CS Lozenets - commissioned in November 2021 

  • On 20.01.2021, a rehabilitated subsection of the gas transmission network VA Batultsi - VA Kalugerovo with a length of about 13 km was commissioned. 
  • On 10.03.2021 began the construction works for the replacement of a subsection with a length of 23 km. The construction works are ongoing. 
  • On 14.01.2022, a rehabilitated subsection of the gas transmission network PF Beglej - VA Dermantsi – VA Batultsi with a length of about 45 km was commissioned, including one pigging facility (PF Beglej).

GENERAL NON-TECHNICAL SUMMARY OF THE PROJECT

Implementing the GUIDELINES FOR TRANSPARENCY AND PUBLIC PARTICIPATION (Annex VI of Regulation (EU) 347/2013), Bulgartransgaz EAD published a General Non-Technical Summary of PCI 6.8.2 Rehabilitation, Modernization and Expansion of the Existing Gas Transmission System

General Non-Technical Summary

General Non-Technical Summary, second edition - 2018

General Non-Technical Summary, third edition - 2022 

 

INFORMATION LEAFLET OF THE PROJECT

Implementing the GUIDELINES FOR TRANSPARENCY AND PUBLIC PARTICIPATION (Annex VI of Regulation (EU) 347/2013), Bulgartransgaz EAD published an Information Leaflet of PCI 6.8.2 Rehabilitation, Modernization and Expansion of the Existing Gas Transmission System

 

EXTERNAL PROJECT FINANCING RECEIVED

PCI 6.8.2 Rehabilitation, Modernization and Expansion of the Existing Gas Transmission System – Phase 2 has been implemented with Bulgartransgaz EAD own funds and the financial support of the EU through the Connecting Europe Facility (CEF) Programme.

IIn April 2016, Bulgartransgaz EAD signed a Grant Agreement No INEA/CEF/ENER/M2015/1119568 for the implementation of Action No.6.8.2-0055-BG-S-M-15. In line with the Agreement the amount of the grant is 50% of the Action value – up to EUR 850 000 (eight hundred and fifty thousand) and it comprises the following three main activities:

  • Preparatory activities regarding the rehabilitation (reinforcement) of the northern semi-ring of the gas transmission system.
  • Preparatory activities regarding the modernization of 3 compressor stations by integrating low emission gas turbine compressor units.
  • In-line inspections of two gas pipeline sections.

At the end of 2018 the implementation of the Action was completed and it has been reported to the financing institution, the Innovation and Networks Executive Agency (INEA) in 2019.

In May 2017, Bulgartransgaz EAD signed a Grant Agreement No INEA/CEF/ENER/M2016/1290626 for the implementation of Action No.6.8.2-0026-BG-S-M-16. In line with the Agreement the amount of the grant is 50% of the Action value – up to EUR 182 000 (one hundred and eighty-two thousand) and it comprises the following activity:

  • Preparatory activities regarding the rehabilitation (reinforcement) of the northern semi-ring of the gas transmission system – a section with a length of approximately 23km

At the end of 2018 the implementation of the Action was completed and it has been reported to the financing institution, the Innovation and Networks Executive Agency (INEA) in 2019.

In April 2019, Bulgartransgaz EAD signed a Grant Agreement No INEA/CEF/ENER/M2018/1749550 for the implementation of Action No.6.8.2-0034-BG-W-M-18. In line with the Agreement the amount of the grant is 40% of the Action value – up to EUR 27 184 518,40 and it comprises the following two main activities:

  • Rehabilitation (replacement) of two sections of the northern semiring of the gas transmission network with an approximate total length of 81 km;
  • Construction supervision.

The rehabilitation of the sections with a total length of about 81 km is carried out consecutively in sub-sections.

 

More Information on the CEF and the projects it has financed

 

PUBLIC PARTICIPATION

Bulgartransgaz EAD published a Public Participation Concept for Project of Common Interest (PCI) 6.8.2 Rehabilitation, Modernization and Expansion of the Existing Gas Transmission System.

 

QUESTIONS AND CONTACT

Comments, questions and recommendations about the PCIs can be sent to the company’s official e-mail address:  info@bulgartransgaz.bg by filling in a Standard Form for comments and questions regarding PCIs carried out by Bulgartransgaz EAD.

 

EC INFORMATION PLATFORM

More information on the PCIs is available on the official webpage of the European Commission.

 

MANUAL OF PROCEDURES

Manual of procedures for the permit granting process applicable to projects of common interest in the Republic of Bulgaria is published in line with Article 9 of Regulation 347/2013, by the Ministry of Energy as the competent national authority.

 

The sole responsibility of this publication lies with the author. The European Union is not responsible for any use that may be made of the information contained therein.