PLANNED INTERRUPTION AT GRS PLEVEN (EXIT)
Activities: Maintenance works on transmission gas pipeline and reconstruction of technological equipment
Affected assets:
GRS Pleven C041P01 - 58ZC041P01PLEN-7
GRS Pleven C041P02 - 58ZC041P02PLEN-0
GRS Pleven C041P03 - 58ZC041P03PLEN-U
GRS Pleven C041P04 - 58ZC041P04PLEN-N
GRS Pleven C041P06 - 58ZC041P06PLEN-9
GRS Pleven C041P07 - 58ZC041P07PLEN-2
Available capacity at the affected assets during the event: 0 kWh/d
Event start: 20.10.2026, 7:00 EET
Event end: 23.10.2026, 7:00 EET
DETAILS ABOUT THE EVENT ARE PUBLISHED ON BGH IIP *
*According to Article 4(1) and Article 4a of REMIT II (Regulation (EU) 2024/1106 amending regulations (EU) № 1227/2011 and (EU) 2019/942), market participants shall disclose the inside information through inside information platforms authorized by ACER.
Information on scheduled maintenance activities along Bulgartransgaz's transmission system
ПЛАНИРАНО ПРЕКЪСВАНЕ НА ГРС ПЛЕВЕН (ИЗХОД)
Дейности: Ремонтни дейности на преносен газопровод и подмяна на технологично оборудване
Засегнати съоръжения:
ГРС Плевен C041P01 - 58ZC041P01PLEN-7
ГРС Плевен C041P02 - 58ZC041P02PLEN-0
ГРС Плевен C041P03 - 58ZC041P03PLEN-U
ГРС Плевен C041P04 - 58ZC041P04PLEN-N
ГРС Плевен C041P06 - 58ZC041P06PLEN-9
ГРС Плевен C041P07 - 58ZC041P07PLEN-2
Разполагаем капацитет на засегнатите съоръжения по време на събитието: 0 kWh/d
Начало: 20.10.2026, 7:00 EET
Край: 23.10..2026, 7:00 EET
ИНФОРМАЦИЯ ЗА СЪБИТИЕТО Е ПУБЛИКУВАНА НА BGH IIP *
*Съгласно Член 4(1) и Член 4а на REMIT II (Регламент (ЕС) 2024/1106 за изменение на регламенти (ЕС) №1227/2011 и (ЕС) 2019/942), участниците на пазара разкриват вътрешна информация чрез платформи за вътрешна информация, оторизирани от ACER.
Информация за планираните ремонтни дейности по газопреносната система на "Булгартрансгаз" ЕАД